Master Project Scheduling
Church Design & Construction maintains an ongoing Master Project Schedule to insure all parties are informed on the current and future process. This aspect of our services is critical. Many congregations get very restless as the project moves forward without any physical site changes. It is imperative that the church leadership and the congregation be kept well informed on the realistic Master Project Schedule and its milestones.
A church development project is a long term endeavor. CD&C separates the development process into 7 separate phases. The following is an illustration of the 7 phases which include a total of "78" line items.
The Master Project Schedule is general and may not be specific to your project.
- Scope of Work Identification
- Schematic Site Drawings of Existing
- Schematic Floor Plan Drawings of Existing
- Schematic Elevation Drawings of Existing
- Schematic Site Plan Drawings of Proposed
- Schematic Floor Plan Drawings of Proposed
- Schematic Elevation Plan Drawings of Proposed
- Government Research & Discussions
- Preliminary Budgeting
- Funding Coordination
- Feasibility Study
- Development Management for Phase 1
- Planning Application Processing
- Government Fees
- Preliminary Site Drawings of Existing
- Preliminary Floor Plan Drawings of Existing
- Preliminary Elevation Drawings of Existing
- Preliminary Site Plan Drawings of Proposed
- Preliminary Floor Plan Drawings of Proposed
- Preliminary Elevation Plan Drawings of Proposed
- Site Boundary Survey
- Artistic Renderings
- Preliminary Landscaping Plan
- City/County Required Studies
- Use Description
- Owner Narrative
- Parking Study
- Traffic Study
- Political Relations
- Public / Neighbor Relations
- Planning Hearing
- Appeals Hearing
- Development Management for Phase 2 (3 months)
- General Design
- Civil Engineering
- Soils Testing
- Government Fees
- Structural Engineering
- HVAC Engineering
Phase 1: Feasibility Study, Schematic Plans, General Scope Identification, Preliminary Budgeting
Phase 2: Planning & Entitlements
Phase 3: Architecture & Engineering
- Plumbing Engineering
- Electrical Engineering
- Title 24 Calculations
- Finish Schedule
- Landscape Design & Specifications
- Interior Design
- Special Testing and Inspections
- Development Management for Phase 3
- Print 10 Sets of Plans for Agencies
- Print 20 Sets of Plans For Pre-Estimates
- Fill Out Plan Check Application(s)
- Plan Check Fees
- Submit Plans For Review
- Obtain Plan Corrections
- Re-submit Plans for Review
- Obtain Plan Corrections
- Re-submit Plans for Review
- Obtain Plan Corrections
- Pay Applicable Permit Fees
- Pay Applicable School Fees
- Obtain Permits
- Development Management for Phase 4
- Print 30 Sets of Plans
- Invite Pre-Qualified General & Subcontractors
- Solicit Bids From Material Suppliers
- Solicit Bids From Labor Companies
- Create A Spread Sheet With All Bids Listed
- Qualify Scope Of Work On All Bids
- Pre-Select Preferred Vendor For Each Area
- Present All Information To Project Owner
- Issue Agreements to Vendors
- Development Management for Phase 5
- Create Construction Schedule
- Issue Subcontractor / Vendor Agreements
- Obtain Subcontractor / Vendor Licenses
- Obtain Subcontractor / Vendor Insurances
- Construct Offsite Improvements
- Construct Onsite Improvements
- Development Management for Phase 6